hi sap gurus,

just i want to change the plant after saving of delivery document and before PGI. kindly give me the solution.

thank you

ramesh

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Dear Netha Seetha

This is not the good practice to change the plant in delivery, but you can change the plant during Sale Order creation and then you can deliver that order.

VA41>VA01>VL01N>VF01

You change at VA02 and then make VL01N

Thanking you!

Ashish Mishra

Former Member
0 Kudos

Dear Ramesh,

once the delivery is done you cant change the plant in delivery but

if your scenario is ls like this u can do

EX:-ORDERED 100

DELIVERED-50 FROM 5000 PLANT.

NEXT 50 U CAN DELIVER FROM ANOTHER PLANT 8000

just go to va02 change the order quantity from 100 to 50 for first line item and then enter the same item in second line and give remaining quantity 50 and plant 8000 and save it, then you can deliver remaining from plant2.

Regards

Rajasekhar

Former Member
0 Kudos
Former Member
0 Kudos

Dear pl check the above given link mainly plz read vamsi what he said