Reg:Progress analysis

0 Kudos

Hi,

I am working on progress analysis part.

I have two wbs :wbs1 and wbs2

wbs1 have 4 activities

A1

A2

A3

A4

wbs 2 have 2 activities

B1

B2

wbs1 have %value from total contract is 9%

And wbs2 have %value from total contract is 91%

wbs1=9%

And for activity in 100 points:-

A1=64

A2=22

A3=8

A4=6

WBS2=91%

and for activity in 100 points

B1=51

B2=49

Now whenever i will do confirmation of activities and get the actual confirmation of particular activities i can able to know the actual completion of particular WBS.

E.G:-For wbs2

B1 =80% COMPLETED=40.8

B2=50%COMPLETED =24.5

So total WBS2 Completed is 65.3%

So in 91% of wbs2 -> 59.423 is completed and on that basis we can do the payment to contractor.

Can you please help me to configuring  this type of scenerio.

What measurement method is required to configure.

Kindly let me know if any issue in understanding my question.

With Regards

Bhaskar ranjan

Accepted Solutions (0)

Answers (3)

Answers (3)

gerry_hodgins
Active Participant
0 Kudos

hello Bhaskar ranjan

You should Note : when talking about the  'Degree of Processing'
There is a restriction in using decimal places
the data element CO_ABARB (which is used for field AFRU-ABARB)
is defined with no decimal places.


you could try re-defining the field element but this could
cause  problems everywhere where this data element is used,


As a workaround, I can only suggest that you implement your own
measurement method via exit EXIT_SAPLCNEV_03_POC_001.

Former Member
0 Kudos

Hi Bhaskar,

Refer below link to know how Project Progress and Progress analysis works.

http://help.sap.com/printdocu/core/Print46c/en/data/pdf/PSPRG/PSPRG.pdf

Regards

Tushar

sanjeevc
Active Contributor
0 Kudos

HI Bhaskar,

hope below link will help you.

http://scn.sap.com/thread/2080544

Regards,

Sanjeev