Hi All,
I need to fix the following:
Suppose i have an activity with basic start date 1st Jan 2012, and not i confirmed the activity on 1st Sep 2012, and then reschedule the project.
System automatically updates the basic start date of the activity to 1st Sep 2012. Is there any setting to stop copying of actual dates to the basic dates on rescheduling the project.
Any pointers will be helpfull.
Thank you.
Regards,
Jatinder
Hi All,
Additional info --> I have already checked the issue by selecting "Shift order" in OPU6, but this dies not work.
Regards,
jatinder
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If I understood correctly, you want to retain original basic dates even after activities confirmed are not following scheduled dates. You want this to compare the actual dates with the original basic dates.
If my understanding is correct, then I suggest to follow following steps:
1) Whenever you are scheduling or rescheduling, please save it as project version.
2) This will enable you to compare the original basic dates with the actual dates and most current scheduled dates.
You can also achieve this by copying basic dates into forecast dates which remains static till the time you do not change.
Regards,
Mahendra