on 09-05-2012 4:01 PM
Hi All,
I want to share one scenarion. User is creating delivery from projects CNS0.In next window in assignment tab, WBSE field is blank. This is happening for particular material , for rest of the material it is perfect.
Procurement type for this particular material is Reservation for network,while for other materials it is Reservation for WBSE. Is this can be the reason?
Please suggest.
Thanks
Hi Akhil,
the system copies account assignments from the reservation into the delivery. As the component procured by 'reservation for network' is NOT account assigned to any WBS-element, the delivery item is also not assigned to a WBS-element.
The characteristics, whether a material is managed in individual stock or in anonymous stock does have influence in the account assignment of delivery items too. The account assignment category decides, what account assignment object is to be used.
Please see the help
http://help.sap.com/saphelp_erp60_sp/helpdata/en/4c/227b8046e611d189470000e829fbbd/frameset.htm
Regards, Gordon
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
The root cause could be setting in MRP4 view ( individual and collective field). You might have maintained 2 ( collective stock) in this field. When such materials are attached in project structure they create plant stock and not project stock. So it will not have any WBS assignmemnt, and the cost will be collected on the network activity when you do the delivery. So you do not see WBS assignment in CNS0.