Conversion of planned order with past date into Process order

Former Member
0 Kudos

Hi,

When I convert planned order with start and finish date in past to process order from APO dates in process order are showing past dates only. I.e. same dates as that of planned order.  In ECC for relevant prodution scheduling profile in scheduling parameter order in past date is not allowed.  But this parameter is not taken into consideration during conversion from APO.

Smiliar planned order if I convert into process order into ECC automaticaly current date scheduling is carried  out.

Is this Standarad Behaviour? Are there any options to have behaviour just like ECC conversion?

Regards,

Santosj

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

I think you have posted the same query again.

Yes right as per standard SAP dates are always determine from the APO. Better do the forward scheduling of planned order in DS board and then convert it to Process/production order.

Or convert order planned order in ECC

Regards,

R.Brahmankar

Former Member
0 Kudos

Thanks for your Reply. I belive when we convert planned to process order from APO it is as goods as conversion happens in ECC only relevant data from APO will copied into order.

So I should have same bahaviour as that of ECC conversion. Is there any where there is clearly mentioned this SAP standarad behaviour. I am looking for any such material.

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Please refer OSS note 382385.

You can use BAdI EXIT_SAPLCOXT_001 (SAP enhancement PPAPO004) to restrict it.


Regards,

R.Brahmankar