cancel
Showing results for 
Search instead for 
Did you mean: 

GRC CUP Email Dispatcher job goes to Busy state

Former Member
0 Kudos

Hi

GRC CUP 5.3 Email Dispatcher job goes to Busy state, Last week it was working fine..suddenly its goes to Busy State.

Because of this There is no email notification to approver..

requestor have submitted an GRC CUP request # , but Requestor did not received email informing the request have been submitted.

Please check and suggest..

thx,

S. Nagaraju

Accepted Solutions (0)

Answers (2)

Answers (2)

saksham
Advisor
Advisor
0 Kudos

Hi S. Nagaraju,

Kindly check the below thread-

http://scn.sap.com/thread/2061938

Hope this helps.

Kind Regards,

Saksham

Former Member
0 Kudos

Hi Nagaraju,

I would request you to please verify that the job

for e-mail reminders has been set up in accordance with SAP Note:

1228952.

Ideally, the recurrence interval for the background job should be more

than the "Background Job Time Interval in Minutes" maintained in

Configuration->Miscellaneous.Kindly check this setting in your case.

Additionally,review the below sap notes realted to the issue which you are facing.

1669990

1666344

1641913

Hope this helps.

Best Regards,

Nandita