on 09-04-2012 4:24 AM
i have deleted the queue from the /SAPAPO/CQ transaction, the queue was relevant to Process order. Then i tried to push this from /SAPAPO/CCR but it is showing the option Delete only. i can not push to R/3 or APO.
Now the order is not in sync. the order is deleted (TECO) in R/3 but it is exist in APO. how to transfer this data to APO.
Dear,
As process order is have having status as TECO it is not relevant for planning in APO. Run the CCR and deleted the order in APO. If want that order to be planned again then go to CO02 restrict processing and revoke TECO and run CCR again.