on 09-03-2012 12:53 PM
Hi Experts,
I have come across the following senario: Though there is an original budget uploaded in CJ30, it does not appear in S_ALR_87013558? For example, when I have allocate an original budget though CJ30 and have released the same through CJ32 I can not see the same value through S_ALR_87013558. What can be the reason?
Further, I want to know whether there is a possibility to change the Budget figure (under Budget column) which appears in S_ALR_87013558 report to release budget value of a project. This will be useful to compare commitments and actual against the release budget.
Thanks,
Dileepa.
Hi Dileepa,
I think for your second question, use the t-code CJE2 to change the Report settings.
Rgrds,
Santhosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
7 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.