Can any SAP PS Guru Explain Me about the table coloum RemOrdPlan in report S_ALR_87013558.

 

Regards

Hamayet Rasel

Bangladesh


Accepted Solutions (0)

Answers (4)

Answers (4)

former_member195427
Active Contributor
0 Kudos

Hi Rasel,

              You may close the thread if your doubts are clear now.

Regards

Ankur

Former Member
0 Kudos

Hi Rasel,

Please refer link mentioned below which is quite similar to your querry

http://scn.sap.com/thread/663771

Regards

Tushar

Former Member
0 Kudos

Hi,

Search forum before posting query.

RemOrdPlan stands for remaining order plan value.

See this for more details-

http://scn.sap.com/message/7915684#7915684

http://scn.sap.com/message/4562677#4562677

http://scn.sap.com/thread/1597457

Regards,

Pranav

former_member195427
Active Contributor
0 Kudos

Hi

Please take a look at SAP note 922177. It mentions how the ROP is calculated. I am not aware any standard transaction or program that can trace the difference. Perhaps you could execute the transaction CJ31 -> Extras -> Availability control -> Analysis. From you could know what is assigned value that coming from ROP and its changes (especially Value Type 25)

Regards

Ankur

Former Member
0 Kudos

Hi,

Please search the forum or refer SAP help. The topic "RemOrdPlan" has been discussed a lot of times in this forum.

Regards,

Gokul

MohanDesai
Active Participant
0 Kudos

Hi Rasel,

Gokul is right. However I am giving some inouts,

The remaining order plan is the value that is the remaining work

outstanding for the network activity - e.g. When you create an

activity and plan it for say 100K and goods receipt 50K - the

remaining order plan will be 50K (100-500.) It is always the plan

value less the actuals.