Hi Experts,

My Scenario is this.

1. 1st Project WBS Element ( Capturing the Cost)

2. 2nd Project WBS Element ( for which the material cost will be capture and this should be transfer to the 1st WBS Element / Activity)

I will procure the material against one project and network. for which i will issue the material against that WBS and Activity.

but i need the cost of material cost should be transfer to the other WBS Element & Activity.

Thanks in advance for the solution.

Accepted Solutions (0)

Answers (4)

Answers (4)

former_member195427
Active Contributor
0 Kudos

Hi CP,

         You may close the thread if your issue is resolved now.

Thanks & Regards

Ankur

Former Member
0 Kudos

Hi,

Above persons are right.

KB11n can be used to transfer cost as per need.

But use of settlement to transfer cost is preferable as you have to transfer all cost of wbs1.

Regards,

Pranav

Former Member
0 Kudos

Hi,

Apart from Ankur's suggestion, you can consider settlement to transfer costs between 2 WBS.

Regards

Shrikant

former_member195427
Active Contributor
0 Kudos

Hi,

  You can transfer cost from one WBS to another WBS using t-codes KB11N & FB01.

Using KB11N you can transfer costs from one WBS to another manually  - on screen set Fields: scrn variant "10SAP All input" and input type "S individual entry".  this variant open 2 section (Sender & Receiver) with all  Objects costs. Modify with KB12N.

You can see value and document using for example with S_ALR_87013542 - Actual / Commitment / Total / Plan in CO Area Currency.

Also refer the following links :

http://scn.sap.com/thread/2127709

http://scn.sap.com/thread/1384761

Hope, it helps.

Regards

Ankur