Hi all,

client requirement is to trigger commitment item based on available budget with out activating FM management. When a PR is trigger automatic on WBS once the GR is executed commitment item is not show under the report.

Does this require a valuated material  with valuation class or non valuated. what is the way out

With regards,

babu

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Also need to define the G/L account determined in PR as cost element.

Regards,

Mahendra

Answers (1)

Answers (1)

sanjeevc
Active Contributor
0 Kudos

HI,

yes you are required a valuated material with valuation class for PR's commitment showing in report.

http://help.sap.com/saphelp_45b/helpdata/en/4c/227bc146e611d189470000e829fbbd/content.htm