on 09-01-2012 4:15 PM
Hi all,
client requirement is to trigger commitment item based on available budget with out activating FM management. When a PR is trigger automatic on WBS once the GR is executed commitment item is not show under the report.
Does this require a valuated material with valuation class or non valuated. what is the way out
With regards,
babu
Also need to define the G/L account determined in PR as cost element.
Regards,
Mahendra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
yes you are required a valuated material with valuation class for PR's commitment showing in report.
http://help.sap.com/saphelp_45b/helpdata/en/4c/227bc146e611d189470000e829fbbd/content.htm
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.