Change Tracking in Manual revenue planning CJ42

Former Member
0 Kudos

Dear Gurus,

Is there any t-code or method by which we can track the document change in manual revenue planning in T-code Cj42. Kindly help me on it.

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member195427
Active Contributor
0 Kudos

Hi Ahmad,

               As far as I know,Tracking change is not possible.CJ42 is just like Cj40 i.e. Cost planning.... data will get save but no documents will get posted. Hence,in this case tracking change is difficult.

Even in case of automatic revenue planning from Sale order or quotation you can not track changes..

Regards

Ankur

Former Member
0 Kudos

Hi Ankur,

Thanks!!! If there is no document generated then you cannot find it by CJI4 or CJ3B.

But every change in any table can be tracked by AUT10-Audit Trail.

Again it is logical requirement

Hi Ahmad,

Use AUT10 for this purpose.

There you can find any change in SAP.

Choose enhancement mode and enter transaction code with other details.

Hope there you find the all the change details.

Regards,

Pranav

Former Member
0 Kudos

Hi,

Try CJI4, add document Number from layout & sort by same.

You can also see documents  by CJ3B.

Regards,