on 08-28-2012 5:20 PM
Dear experts,
We are on SRM 7.01 & ECC EHP4, extended classic scenario and business function
LOG_MM_P2PSE_1 is still not yet activated.
I would like to know whether the mentioined version of ECC will still support the external requirements via old fashion i.e. mainiting the entries in
V_T160PR & V_T160EX & running a report bbp_extreq_transfer.
Kindly advice me,
Regards,
Krish
Hi,
Yes. ECC EHP 4 supports PDP process.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes, you can still transfer PR using report BBP_EXTREQ_TRANSFER.
Thanks,
Sushil.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.