Error Budget Transfer CJ34

Former Member
0 Kudos

xxxxxxxxx-01-02-03 to xxxxxxxxx-02-13

Error while transfering budget from WBS to WBS

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member221039
Active Participant
0 Kudos

cj34 is used to transfer budget from one WBS element to another WBS element in same fiscal year ideally.  In case you want to transfer from previous to current fiscal year, best option to do cjcf & cjco (budget carryforward).

Former Member
0 Kudos

Hi Ravi,

Please post your query with full detail so that one can help you.

Regards,

Pranav

former_member183901
Active Participant
0 Kudos

Hi Ravi,

Could you ask your question in a proper way so that forum can understand to answer it quickly?

Thanks in adv.

MRD

former_member195427
Active Contributor
0 Kudos

Hi Ravi,

          Please give the error message number or if possible, provide screen shot.