Dear All,

                  Is there any report in SAP PS , in which advance details are coming given against PO for any particular WBS element .

Thanks & Regards

Shailesh

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

You can use SQVI for making such customized report.

Table name-BSIK.

Field Name-DMBTR.

Regards,

Pranav

former_member203098
Active Contributor
0 Kudos

txn cji3 extras--select value type as 12 and run the report for the project/wbse. In the report output you can find the downpayments line items against the purchasing documents for thisproject/wbse.

regards,

mandar_mahuli
Participant
0 Kudos

HI shailesh, you can try below report and let us know its helpful or not  S_ALR_87013536 - Plan-Based -> Hierarchical -> Plan/Actual/Down Payment as Expense   regards, Mandar

Former Member
0 Kudos

Check the CJI3 report. Filter the output based on value type. Choose the correct value type for down payments and see it shows in the report.