Hi,
There is any way to calculate forecast percentage of completion in any project using dates of baseline project and current date?
Thanks a lot,
CAMILO URIBE
Hi Camilo,
in cProjects there are two key figures as far as I recall:
Besides you can work with alerts and use arbitrary formulas there. See customizing: Project Management -> Evaluations. There is also a BAdi available there.
Best regards
Thorsten
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Thorsten;
Can you make a calculation of percent completion (%) with the tasks of Project like Microsoft Project does?
I think that Camilo asks if its posible to do that?
I have the same question, maybe with an Enhancement. I don't know if Evaluations can be usefull, maybe an BCV report can help us.
Best regards.
Mariano
User | Count |
---|---|
11 | |
6 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.