Hi Experts,
Is there is a way to revoke the release of budget? For example: If I wrongly release a budget of 60 out of original budget 100, is there a way revoke the relase back to 40.
Thanks,
Dileepa.
Hi Dileepa,
I assume you can revoke = change the released budget in CJ32. At least as long as availability control does not hinder you.
If you have released a budget of 60 and 'consumed' this already, I expect that the availability control might give an error (depending on your customizing settings). Otherwise it should work.
Best regards
Thorsten