on 08-22-2012 10:15 PM
Hi All,
We are doing finite sched on the planning board for a couple of our time-cont resources. When we convert a finitely scheduled planned order into prodn order the prodn order that comes back from ECC gets a "De-allocated" status. We want it to be allocated & not overload the resource, which it does when in the de-allocated status.
We use "Find Slot" mode on out strgy profile - FYI.
Any idea what could be causing this issue?
Thanks
Hi Andy,
Are you converting the order in APO or in ECC? What you are describing is actually standard behavior if you change the order in ECC. See SAP Note 753626.
https://service.sap.com/sap/support/notes/793626
Best Regards, Mike