on 08-21-2012 6:08 PM
Hello All,
In the project planning board activity relationship, i double click on the activity relationship say FS, and then add offset to -2 days (minus 2 days), i see the figure 2 without MINUS sign before it. In another system i can see the figure with MINUS sign, any idea on setting to set this to - if the figure is minus and only figure without any sign when the value is positive.
Regards,
Jatinder
Hi Jatinder,
I tried your scenario in IDES, entered -2 Day and system made it 2- day. Please check if minus sign is after 2, alternatively try to give 2- instead of -2.
Regards
Shrikant