on 08-21-2012 7:50 AM
Hi,
I created control plan using QPCP transaction. I clicked on FMEA Tab and assigned the FMEA in the control plan. The traffic light status is coming in red. Kindly let me know where i am going wrong.
Regards,
Pragalathan
Hi,
This is because of Non transfer of Characteristics from FMEA to Control Plan...
Refer below link for process:
Check & revert.
Regards,
Anup
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Pragalathan,
Please refer below link & check if you can copy characteristic from FMEA to CP.
http://help.sap.com/erp2005_ehp_04/helpdata/EN/07/bda6c52333422e8fc12f39e51f39a4/frameset.htm
Regards,
Anup