Hi Team ,
I am facing an issue in my current project , where in a component is planed in the project , with procurement type " PR + Reservation for WBS element".
with this ,a reservation number(demand) and PR(Supply) number were genreated in CJ20n .
The issue is , MRP has genreated another purchase requistion for the reservation number and has not considered original (project) PR.
This is resulting in mutiple purchase orders for the same requirement .
Kindy let us know your suggestion /views to resolve this issue.
Thanks
Ameet SK
Dear Ameet,
As Sudhakar Suggested this may be some missing/ wrong setting in MRP so this is creating duplicate PR for same material.
thanks
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check with your MM/PP team for MRP settings that might causing duplication of PRs against one component.
I am sure you can transfer this issue to either MM or PP forum so that can be addressed.
Regards,
Sudhakar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.