We already have different types of calendar in PPM. Their use depend of the project that we select. However, sometimes some projects need to enable some no-working day (For instance, weekends) in order to execute specific activities.
Is there any way to enable this days only for this project?
Thanks,
CAMILO URIBE
Hi Camilo,
you can assign the factory calendar not only for a complete project, but e.g. also phases / tasks. So basically that should be possible by assigning the 'right' factory calendars.
Best regards
Thorsten