on 08-17-2012 7:51 AM
hi all,
how can i report revenue compare to the actual costs which i get after confirmation.
thanks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Run tcode GR55 and choose report group as 6P01 and execute. Enter the project number and execute the report. Here you will get a detailed cost element based report where you can compare revenue to actual costs. There are other reports too viz., S_ALR_87013531, CJI3.
Check CJI3 report also. Here you can compare the figures based on value type and debit type.
Regards,
Gokul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Abhinay,
All actual costs, actual revenues also can be checked via CNS41.
Best Regards,
Edna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Try this-
S_ALR_87013564 - Plan/Actual/Variance
S_ALR_87013568 - Project Results
Regards,
Pranav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.