Project budget restriction against cost elements and document types

Former Member
0 Kudos

Hi Experts,

Can budget restriction be omitted for certain cost elements or for posting based FI document types?

Thanks in advance,

Mike.

Accepted Solutions (1)

Accepted Solutions (1)

schneidertho
Advisor
Advisor
0 Kudos

Hi Mike,

I guess you refer to avaliability control in PS. Yes. You can have exempt cot elements there.

See customizing: Project System -> Costs -> Budget -> Specify Except Cost Elements.

And you can have different tolerance limits depending on activity groups (e.g. financial accounting documents). See Customizing: Project System -> Costs -> Budget -> Define Tolerance Limits

Best regards

Thorsten

Former Member
0 Kudos

Hi Thorsten,

Thanks for your reply. Yes cost element exclusion worked clearly. However, if possible I want to know the posibility of excluding FI posting which are done using specific document types.

Thanks,

Dileepa.

schneidertho
Advisor
Advisor
0 Kudos

Hi Dileepa,

I would not vouch for it (since my active days in PS are over) - but to my best knowledge there is no standard possibility for that.

I have also checked user exit SAPLBPFC, but at first glance it does not seem to give you the needed information to implement a logic basde on document type.

Best regards

Thorsten

Former Member
0 Kudos

Hi Thorsten,

Oh ok, in that case I believe only option is to use OPTK and OPI2 to exculde FI posting through cost elements.

Best Regards,