on 08-16-2012 11:07 AM
Hi ,
I am beginer in Project system. I have done basic setting and now i am trying to integrate Project system with HR. can anyone help me in integration part, My scope is to reflect employee salary from HR to Budget of project in Project system. Plz guide
Mukul
Hi Mukul,
If you are using CATS then specify reciever WBS in CAT2 or use periodic assessment & Distribution process of CO or KB11N for manual Re-posting of cost from cost centre to WBS.
It is already discussed in detail on http://scn.sap.com/thread/1183484
If any query then repost here.
Regards,
Pranav