Upgrade Solution Manager from 7.0 to 7.1 Error in Postprocessing Phase

Former Member
0 Kudos

HI All,

Upgrade Solution Manager from 7.0 to 7.1 Error in Postprocessing Phase. The Abap operation is successfully completed, but the java failed.

Please find the screenshot.

Regards,

Rian W

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Vikram,

Thx for the reply. I have fixed the problem.

1. Exit Upgrade GUI.

2. Stop Upgrade tool

3. Stop SAP

4. Restart Server

5. Start SAP

6. Start Upgrade Tool

After that I can continue the upgrade.

Regards,

Rian W