Dear All,
Requirement - I need to supply some raw materials to an external vendor and need to issue a finished material to the project.
Need to understand how to execute such a cycle, do we need to assign the raw materials as non-stock materials and generate PR ...... i am not clear on the ewxecution steps.. i will appreciate of someone can list down the high level steps to execute this cycle,...
Thank you.
Regards,
Jatinder
Hi Jatinder,
Subcontracting material will be assigned as stock item. Its BOM will have raw material as items. MRP will generate PR for sub con matl and dependent requirements. The raw material will be procured and sent to vendor. Finally subcon matl will be received from vendor. Discuss the process with your MM consultant.
Regards
Shrikant
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Good replied by Shrikant and Sunil, According to them process flow will be following:
Subcon. Testing Procedure | |
me51n | PR |
me54n | PR Rel. |
me21n | PO |
me29n | PO Rel. |
migo | GR |
mmbe | Stock check |
me21n | PO subcon. |
me29n | PO Subcon. Rel. |
mb1b | stock transffer 311----------q--------tpty |
mmbe | Stock check |
j1if01 | Challan click on print immediate before saving |
spo2 | spool request generate |
migo | GR would be receive in SFG mode or own mode |
j1ifq | Reconsulation materials |
Regars,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Jatinder,
In standard SAP, it is not possible to use 541+Q (Q refers to Project Stock) to transfer Project stock to subcontracting vendor as Simple Subcontracting.
So, it is recommended to create new storage location to each subcontracting vendor & use 311+Q movement type, based on this it is possible to monitor stock at subcontracting vendor.
Create PR with A/c assignment “Q” & Item cat "L" or Direct PO creation
Create PO (A/c assignment “Q” & Item cat "L")
Release PO (if release strategy exists)
Define new storage location for Subcontracting Vendor
Transfer posting components to Subcontracting vendor with 311+Q
Check the stock with Subcontracting vendor using Tcode MMBE (not with ME2O)
Create Subcontracting challan with ref. to material document
Print out of subcontracting challan
Receive final product against subcontracting PO with 101 movement type
Reconciliation of challan
Complete the challan
Check status of challan
Please check this scenario for Subcontracting using Project stock.
Thanks
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Jatinder,
please describe a little bit more in detail what the process is.
when do you want to post the GI to the project? at the same time when posting the GI for sending the raw materials to the vendor? Why are you sending raw materials to the vendor?
At first it sounds like a subcontracting process. You send raw materials to the vendor and he will do something and send you a finished good back (SAP-Standard). When you have the finished good on stock, you can post the GI for the project (also SAP-Standard).
best regards
Matthias
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.