on 08-15-2012 7:07 AM
Hi Experts,
We use Factory Calendar assigned in APO Planning Calendar (Time Stream).
When there's update in Factory Calendar from R3 to APO, in order to update the buckets in the APO planning calendar accordingly, how to refresh the APO planning calendar?
Your input is appreciated,
Thanks
Mandy
hi,
you need to transfer the changes ( For eg: if there has been a new entry for holidays or more working days), you need to first transfer via RSA1 in APO.
you could use the program
/SAPAPO/TIMESTREAM_UPDATE
if there are inconsistencies between calendar assignment for plants and DCs you have to manually go to the /sapapo/calendar and regenerate "calculate periods"
also please check in rule determination if you are using GATP.
regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.