Dear Team,
I am configuring in APO system to transfer the planning results to R/3. In SPRO, i have done the publication for the plant, publication type with target logical system (R/3). Also i have generated the publications in the t.code SAPAPO/CP2.
In order to receive the planning results in R/3 from APO, should i need to configure anything in R/3 side.
Note: R/3 Master data is transfered to APO successfully.
Thanks
Hi,
Does the corresponding integration model exist in r/3 which represents this transaction data???
Also do u find any errors in publishing back to r/3 in sapapo/ccr???
Thanks,
Bye
Sandeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
PSK,
1. Pls check the settings in PP/DS Global settings in SPRO for Transfer Events. (Maintain Global Parametrs and Defaults --> Transfer to R/3 In-house Production)
2. Pls also check the offset duration in /sapapo/RRP7 -- when trying to transfer the Planning Results to ECC.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
PSK,
In order to receive the planning results in R/3 from APO, should i need to configure anything in R/3 side.
Of course. Any object you send to R/3 must first be configured in R/3. Purchase reqs, planned orders, Planned independent requirements, whatever. You should be able to create any of these objects in R/3 manually, without error, from within R/3, before you even think about sending them from APO. As implied by expert Sandeep, the core interface will usually tell you when there is a failure to successfully load the objects into R/3.
Best Regards,
DB49
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.