Hello, I understand that CJ9B would not copy any Easy Cost planning data but only plan data coming from cjr2 ( or similar) tranactions.
Does anyone knows how to copy ECP plan data by period into a different or 0 version?
Thanks in advance.
Dear Ankush kapoor,
It's possible to copy ECP data via CJ9F or CJ9FS, but unforunately these are not per period.
Please review note 381430 for related informations.
Best Regards,
Edna Jin