on 08-07-2012 2:59 PM
Hello,
I need some help here, please...
I'm upgrading my SSM to version 7.1 SP5 and the upgrade process has stopped on the MAIN_NEWBAS/PRODCHK_UPG phase.
Just before it stops, the upgrade process issues this warning:
WARNING: change request /0/SAPK-S7205INCTSPLGN not removed from upgrade buffer.
I press "continue" and then the process stops with message:
Checks after phase MAIN_NEWBAS/PRODCHK_UPG were negative!
Any idea on how to solve this?
thanks
Antonio
OK, the solution was to rename the transport buffer and create a new one...
After that, the upgrade continued...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Guys,
The detailsed answer is.
1) go to the upgrade transport buffer directory
/SUM/abap/buffer
2)Edit the file <SID> (for Eg: DEV), there you can see a line /0/SAPK-S7207INCTSPLGN........
3) Just comment out that line like (dont comments any other lines)
#/0/SAPK-S7207INCTSPLGN.....
4) SAVE and Continue the upgrade
Thanks,
Naga
Antonio,
Are you using the latest available kernel release for the upgrade?
What is your starting Solution Manager release?
Regards,
Josh Fisher
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
10 | |
10 | |
10 | |
7 | |
6 | |
6 | |
5 | |
4 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.