Case:
I have a project which includes the following:
1. Project Structure: WBS and Networks (Activity Assigned)
2. Budget Availability Checks for PR and PO (at annual released amount)
I have planned some materials (item cat L with valuated project stock) for USD 2000 and services for USD 4000. When I run the report S_ALR_87013533 (Plan/Actual/Commit), it shows the following:
- Materials: Commitments and Assigned Values at WBS = USD 0 (which is correct)
- Services: Commitments at WBS = USD 0; Assigned Values at WBS = USD 4000
When I allocate USD 5000 budget to the project and release the amount of only USD 2500, the system throws an error of budget exceed for the WBS element (Services) by the amount of USD 1500 just because of the assigned values.
Similarly, when the PR (not converted to PO) for material is closed, the system reduces the commitments and assigned values for the WBS, however, in case of service PR close, the system reduces the commitments and not the assigned values.
Desired Outcome:
System should change the assigned values for the services at WBS element level when ever the commitments are updated.
What is needed to achieve the desired outcome?
Regards
Shoaib
Solved the issue of Assigned Values of Service Activity prior to Service PR for the WBS element. It is concerned with Order Value Updating for Orders
Following config settings are required:
1. Check the Planning Indicator in the Network Type (TCode: OPSC)
Use this indicator to specify that you are only using the network for planning. All of the planned costs from this network will be appended to the WBS element, however, they do not raise the assigned values.
2. Un-check the Order Planned Value as Assigned Funds in Order Value Indicator (TCode: OPSV)
If you select this indicator, the plan values for an order with status "Opened" are entered in the assigned values for the PSP element as order requests.
Regards
Shoaib
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi sohib,
when PR make commitment will come in report in S_ALR_87013533
PR delete commitment remove from report S_ALR_87013533
once you complete PR into the PO then assign value will update in system check report
assignment value will update only in that case when PR convert into PO case.
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.