on 08-05-2012 1:25 PM
Hello Experts,
I searched the forum and also aware that the costs posted to the lower level WBS elements can be fetched for a custom development only by using the corresponding wbs. But my client's requirement is only to have a report upto level 4 whereas costs are posted at 6th level WBS element. In this case, how can I get the costs against 1-4 levels where costs are not posted directly and it always carries the rolled up costs. Is there any way to get the rolled up costs (as shown in our S_ALR reports).
Also, I searched for a function module for actual costs which I could not get.
Thanks in advance.
Regards,
Vinodh
Hi,
On the main scren of the reports, try to restrict the levels 1 to 4 reports so that it will display the WBS elements upto level 4.
If it does not work already our friends has suggested how to acheive this.
Regards,
Sudhakar
Message was edited by: Sudhakar Pappu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Vinodh,
Developing Z report is the only solution.
If you state actual requirement with scenario then we may provide you some other solution.
Regards,
Pranav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I would suggest you to develop a custom report to achieve this. In the report output, display WBS's only from 1-4 and write the logic in such a way that i considers/sums up the costs posted at levels below 4.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.