Steps to start a Project

Former Member
0 Kudos

I have some questions

What are the steps in an implementation of SAP MII

How much is the average time duration of an implementation and how many people are doing the project.

Regards, Victor

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Thanks to everyone

Regards, Victor

Former Member
0 Kudos

Hello Vic

The   implementation of the  projects    depends what the client wants.  the whole project  can be broken  into three phases

  • TDS  and DDS  documents
  • development
  • testing
  • sign off

the development and testing usually takes  lots of time  for they are numerious  changes and bug fixes. in simple   short projects  should take roughly 3 months  to complete and major one   7 months.

but this goes with the project cost and business requirements. 

aravinth_anandhan
Active Participant
0 Kudos

Hi,

Benefits of SAP MII

Short amortization time: SAP MII can usually be implemented within 90

to 120 days and therefore pays for itself very quickly.

I read the above point in SCM380 material. Even though they have mentioned 90 to 120 days, it is completely depend on your project requirement.

Regards,

Aravinh

Former Member
0 Kudos

We did our implementation in 8 months and I was the sole person working on it. The scope was about 20 pages some fairly basic and some really complicated.