on 08-02-2012 3:41 PM
Hi,
We have operation A and resource X and operation B having resource B.
Now user is scheduling the order manually in the ds board for the resource A. After rescheduling the operation A the operation B for same order is not getting rescheduled.
So may I know what setting can be done to do this to move the operation B after rescheduling of operation(i.e activity).
Regards,
Sunil Patil
Hi Sunil,
please do the following:
Procedure
This is the Use of the setting:
If you choose this option the system has to take the time relationships into
account between the operations of an order when planning. That is, the system
has to carry out the (re)scheduling of an operation so that the minimum
intervals or maximum
intervals are adhered to:
The answer of Claire is not correct.
BR Frank
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In the strategy profile go to the 'Strategy Parameters for Dependent Objects'. Here check the parameter 'Retain Current Modes'.
Claire
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.