MIVs issued for Stock items against CAPEX Project

faisal_khan
Participant
0 Kudos

Hi,

I created a Work Order using tcode IW31 against CAPEX Project (WBS Element) with one material in the Components tab.

Our company has set a single GL account for all CAPEX projects.

The Work Order was Released so that Material can be issued and a Reservation number was generated. When i see the details of this Reservation using tcode MB23, it shows GL account other than the one set for all CAPEX projects.

Is there a way to change this GL and from where exactly was this GL picked up as I did not mention any GL while creating the Work Order.

Thanks

Faisal

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,Faisal

you have selected Material in the component tab of the Maint order,actually in material valuation class the G/L has been assigned.When ever you select that material concerned G/L has been assigned.

Regards,

K.Sunil