Hi friends,
In my Project budget is releasing based on requirements Like stages wise,then my user is asking that how can they see the stages wise/period wise report ,suppose today they release 1000000, and next week again they will release another 2000000 , so he wants to see date and how much money has released on that particular date and same like in the next week also.
I tried in CJI8 but its showing all he is getting confuse ,is there any way to see the released budget like asked ,if it is there please suggest .
Thanks.
Hi Srikanth,
Try this-
1. In T-code s_alr_87013560.
2. Select release amount for which you want to see detail.
3. Then GOTO->Line Items.
4. Add document number in layout and sort by same. Here you can see date wise & WBS wise release report.
Regards,
Pranav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.