ppds requirement

Former Member
0 Kudos

Hi Guys,

There is a requirement as follows,

Multiple products are manufactured at the same resource. So all the orders are scheduled on the resource which runs 8 hrs a day. We need to do maintenance activity order after every 75 hours of run time which is 9+ days. system should show the order which is at 75th hour. so after that order we can do the maintenance activity done which is manual. Actually the resource should take a load of 75 hrs then manual maintenance activity. But the order will be scheduled in a sequence continuously. is there any way to do it?

Regards

Shruths

Accepted Solutions (0)

Answers (2)

Answers (2)

0 Kudos

Hi,

I am not an expert, but try this

Define a shift for 8 hrs

Define another shift for 8 hrs, but with a break pattern after 3 hrs (and break time of say 1hr).

Define a shift seq for 10 days, first 9 days will have the first shift definition

                                            10th day will have the second shift definition

use this as ur capacity variant .

it is an interesting question, plz let me know if this works for you.

this will not consider the actual run time, it is a periodic definition irrespective of actual utilization.

thanks

Sreeram 

frank_horlacher
Employee
Employee
0 Kudos

Hi Shruthi,

the Clean-Out Order Creation  could solve your requirement.

http://help.sap.com/saphelp_scm70/helpdata/en/e5/e28d6bd43911d6b2c400508b5d5211/frameset.htm

BR

Frank