Hi experts,
Our client wants to know that how many products(semi finished products) and how much of the total production is pending.
In which report we can show the details against of the project, is there any standard report available or we have to go to the customized report.
If customized report then please give some road map on this issue.
Thanks in advance.
Hi,
You can also check %age of completion in CN47N by using column "Processing % of Work".
Here you can set up your layout Work, Actual work, Remaining work and processing % of work.
With these columns it would be able to review what level of work has progressed against planned work so far.
Regards,
Sudhakar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check MD4C to check progress related to materials.
Regards,
Mahendra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check CN41N
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.