You cannot complete a QN before all tasks are completed for it.
Go to QM02, click Tasks tab. Check which tasks have not got status TSCO. Select them and click the complete option at the bottom of the screen.
Once all tasks are status TSCO, you can complete the notification itself
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks a lot, I am able to complete the notification.