Your help needed badly........(((

I'm using SAP PPM 5.0. I have created some Items & created cProjects Projects, PS projects through mapping(Automatic) . IT was working properly earlier. But noew I donno what went wrong suddenly..!( When I make some changes to the existing Projects in the cProjects(Accounting Int done) Its trowing a Dump as, "Field symbol has not yet been assigned". I'm really worried guys. Because, I have so many backups for many projects. Now if its started throwing this kind of dumps & al I cant work properly.

For all the Projects its showing the same thing. Please help me. Herewith I'm attaching the screenshot of the Error message. .

Rgrds,

Santhosh

Accepted Solutions (1)

Accepted Solutions (1)

schneidertho
Advisor
Advisor
0 Kudos

Hi Santhosh,

error is thrown during calculation of attributes for evaluation. Have you changed the configuration for that lately? Have you created any customer-specific attributes in the evaluations?

Best regards

Thorsten

Former Member
0 Kudos

Thank you Thorsten, its working fine now..

Rgrds,

Santhosh

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

I am getting the same dump. i changed the field control group for customer specific requirement.