I have a requirement of mainataining multiple rates for the same manpower in different projects.I am working with EHP5.I found a BADI released in EHP3, BADI_ACT_PRICE_CK -->BADI to process the value with which the costs of a network activity are calculated.

Has anybody utilised this BADI or Is there any other way to influence the activity type rate used in Network Costing?