I have a requirement of mainataining multiple rates for the same manpower in different projects.I am working with EHP5.I found a BADI released in EHP3, BADI_ACT_PRICE_CK -->BADI to process the value with which the costs of a network activity are calculated.
Has anybody utilised this BADI or Is there any other way to influence the activity type rate used in Network Costing?
Hi!
Process wise I am a bit surprised why such a requirement?
Still, to map this without any enhancement one can use different cost centres for different projects as activity type rates are specific to projects.
OR
If you are forced to use same cost centre for all projects once can different activity types for different projects.
Shortcoming for both of above methods: More master data and more maintenance.
The give BADI influences cost plans and not actual costs, so I am afraid it is not very useful.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
I want to influence the Planned Costs only.During Tendering the rate at which the manpower is costed will be carry forwarded to the Planning of different projects.The Manpower would be costed depending upon the location of the projects.The same Concrete Finisher will have different rates in two projects.
Dear Mahendra,
We achieved this requirement through the BAdi. We didnt go for different CO versions as in report again we should enter different planning versions while executing.On feasibility analysis we found that maintaining different rates will be easy than mainataining multiple versions.
Thank you all for the Inputs.......