on 07-25-2012 5:54 AM
dear gurus,
I created one finished product.in that i gave
costing lot size = 100
price unit=100
so the standard price = 6109
but while creating sales order, it is taking 1 unit price = 61.09??
can anyone tell me , what i need to do?
thx in adv...............
HI
In your case if price unit =100 and is equal to 6109, then as simple mathematic says price of 1 unit or BUM is 6109/100=61.09 and the price for customer is maintained in VK11 which reflects in Sales order.
Regards
Anupam Sharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
In Material master . since price unit is 1 so price is 61.09. while in running cost estimate you have given costing lot size as 100 then it becomes 6109.but material master will update only by 61.09 per unit. also in ck13n you can change the costs based on =user entry then enter 1 then you will get 61.09 as 1 pc price.
Check and revert
Regards
Anupam Sharma
Hi
What is your BUM,system will update price according to that. if it is pc then system will update price per pc in MM whatever be your costing lot size.In your case it is NOs and your costing lot size is 100 Nos so standard cost per NO will be updated in MM after cost estimate run.
Check at your end and correct me if am wrong.
Regards
Anupam Sharma
Dear,
Increase the price unit in the material master in accounting to the costing lot size of product costing. Currently it is one make it 100 and then try the same . I hope it will solve this issue.
Else I am not sure but please try Pass on Lot Size setting OKKN
You have to selecte costing variant for the costing run. The Pass on lot size indicator is set in this costing variant
Please refer this link for details,
http://help.sap.com/saphelp_46c/helpdata/en/b2/9d466f0e18d311ae620060b03c9bbe/content.htm
Regards,
R.Brahmankar
Dear,
Price Unit = 1 does not lead to any complications.To avoid the rounding differences if you used for example materials having a low price and a high price unit. For instance, a price of 0.40 and a price unit of 1000 for the material are rounded to a price of 0.00 and price unit 1.
So better to go ahead with unit price as 1 .
Regards,
R.Brahmankar
Dear,
If you have the unit price as 1 or 100 it doesn't make any differences in sales order costing.
Apart form that just do small test If you have already taken the cost run for current period please delete it. After that maintain the Unit price as 100 save the material master and then take a cost run and try to update the price in material master.
Regards,
R.Brahmankar
Dear,
Yes for costing run of 1 qty system is taking the Value as 0.24
If you check the BOM base qty in Header it would be 100 qty
so that for 100 qty of header RC PAD requirement is 24.010
for 1qty as per the ratio RC pAD requiremny is 0.240
If the base qty of header is 1
Then check the SU3 setting
Dear mmboy,
When comes to standard costing of a product,its purely based on the lot size defined in the
BOM,BOM components quantity ,routing and the overheads defined.
In your case since the BOM defined is for a base quantity of 100,then when the cost estimate is
carried out for costing lot size of 1,then the system calculates the BOM components and its value
accordingly,since the BOM base quantity is equal to 100.
There is no logic in just expecting for a quantity of 1 the price has to come as 6109 in the sales
order.
If the BOM defined is for a base quantity of 1,then the value will be coming automatically as 6109.
Other than this I don't think there is some other possible means.
Regards
Mangalraj.S
Hi,
In my understanding, In any case system will update Standard price per BUM as 61.09. when you do BOM base qty as 1 then again accordingly your components qty will change that will lead to again change in standard cost, so its better to ask your client PPc and costing deptt for per BUM price and do the setting accordingly.
Regards
Anupam Sharma
Dear mmboy,
In order to bring or in order to make the product price in the sales order as 6109,you should not
change the standard BOM (used for MRP,Production,costing) base quantity or the BOM component's
quantity which is not the correct practice.As per your master data setup the system derives the cost
values.
So I don't agree in changing the BOM base quantity in your case.
Regards
Mangalraj.S
Dear,
Base quantity of BOM will be applicable for all components if you have the problem with one BOM component then change quantity or price of that item it self to get correct costing. If you change base quantity of BOM so you will have incorrect component quantity order for all BOM components. So if you have correct quantity of component in BOM with base quantity as 100 then please don't change it.
Apart form that this cost will be for standard cost for this finish product. For sales order please have look on your condition type and access sequence unit price and value.
I hope that will solve your issue.
Regards,
R.Brahmankar
Dear,
Costing lot size and price unit will be useful fro costing purpose. For sales order it will be driven by condition type.
Go to V/06 check condition type setting there.
You can maintain selling price in material master. Select Sales: sales org.1 view there there is a field "Conditions".
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.