I have 2 materials A & B.
A Is Stockable item (will use from inventory) & B is Non stock item..(will procure project wise )
My requirement is
when I assign Material A under activity it should automatically generate only reservation of WBS & for Material B it should automatically generate Requisition + reservation for WBS element.(Without Prompting).
I have setting as follows.
In OPS8
Prioirity plant - 2
Prio project - 1
Prio sales ord – 3
And under control data all are untick.
Item category as L
And for both materials in MRP4 tab Individual/coll as 1.
Please sugget.
Regards.
In your test system try changing the setting Individual/Coll in MRP4 tab for the repective material and check what happens.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Gokul,
I checked with
Individual/Coll as blank -sytem prompt for Res for network,res for wbs,req+res for wbs, prlim preq for wbs,3 rd part req wbs
Indvidual/Coll as 2 -system generates automatically res for network.
& also for both Materials master in MRP2 tab Proc type is X -Both.
Please suggest.
Regards,
Hi Mahindra,
I tried as below.
For Material A(stockable item)
Proc type as E & ind/collective ind=1
&
For Material B(Non stock item)
Proc type as X & ind/collective ind=1
It works.
when i assign Material A with item category L it creates Res for WBS & Material B with item category L it creates Req+Res for WBS.
Thanks.
But only one doubt if suppose Management has decided that for some projects Material A will be procure project wise.in that case how to proceed. i tried assigning Material A with Item category N it shows error "Material 1943 is incompatible with item categ (check entry)" as Proc type is E in MRP2 tab.
Please suggest.
Regards,
In case you want material to be procured as Non-stock, you can not choose procurement type E as suggested by error message(as you have declared it as inhouse and inhouse production can not be non-stock).
In this case, it is desired to have procurement type as F. But if you choose procurement type F, system will prompt you for 2 options at least 'reservation for WBS E' and PR+reservation for WBS E'.
You cannot have liberty of selecting item category(N or L) with the above requirement.
Regards,
Mahendra
In case you want material to be procured as Non-stock, you can not choose procurement type E as suggested by error message(as you have declared it as inhouse and inhouse production can not be non-stock).
In this case, it is desired to have procurement type as F. But if you choose procurement type F, system will prompt you for 2 options at least 'reservation for WBS E' and PR+reservation for WBS E'.
You cannot have liberty of selecting item category(N or L) with the above requirement.
Regards,
Mahendra