Hi Friends -
Off late we are observing that the standard rescheduling job is picking up orders which are not on ATP and it even pushes the delivery date forward and because this the delivery creation jobs are not picking up these orders.
Any pointers where should i be looking at ?
One thing i observed is that the job has picked up all the materials/items in sales order and pushed their dates forward. The customer is not marked for Complete delivery.
Thanks
Will OSS 1491650 - V_V2 / SDV03V02 - non-selected materials in the result list answer you question?