Diffeence between Schedule save to call and scheduled call in Preventive maintenance Plan?

Former Member
0 Kudos

Hello Gurus,

Can anybody explain me the exact difference between "Schedule saved to call" and "Scheduled called"  in  maintenance  Plan?

Regards,

Bhanu Pradeep.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

When you made Completion Requirement in maintenance plan, system will not call all the objects immediately. That time, it will keep the scheduled calls in buffer. In this case, the status will be Schedule saved to call.

Either you closed previous orders or you have not selected Completion requirement in maintenance plan, the calls will have status as Called.

http://help.sap.com/saphelp_erp60_sp/helpdata/en/3c/abb531413911d1893d0000e8323c4f/content.htm