Validation in Movement Type 415: Project WBS and Plant

Former Member
0 Kudos

Dear Experts,

We have created project and in plant 0010 is assigned in WBS of Project. Store person of Plant 0040 has transfer his normal stock to this project (having assignment of plant 0010) with the help of movement type 415 in plant 0040.

Now, system has showing material under project in plant 0040.

We have checked authorization object, with authorization object we are not in position to restrict movement of material.

Is any method by which we can restrict material movement in other plant for this project.

Say, plant 0040 person can not transfer own stock to project stock for project having different plant assignment.

Thanks,

Dipen Shroff

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

I think there is no control in std SAP even though stock exists in another plant.

Please use following enhancement spot "MB_ES_TRANSFER" to restrict such goods movements.

Regards,

Mahendra