on 07-19-2012 8:37 AM
Hi,
Commitment is active in controlling area.
budget tolerance is maintained for ++.
AVAC is active.
When i raise pr from project by releasing the activity, no pr commitment gets generated. Even PO commmitment is not getting generated.
I check avac analysis.
PR value entry is coming in red as:
COSP 2012 01 0000300040 KPPE D INR 10.778,80 INR B
here B refers to Plan Costing Single Position.
Kindly help me resolve this issue.
Thanks,
Harsh.
Hi,
I found the problem source. Actually wrong g/l is assigned to the material; it was P/L nature.
I asked FI to put correct g/l of balance sheet nature in material.
Now everything is working fine.
Thanks for all you inputs.
Regards,
Harsh.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
see SAP notes 955107 and 1227760.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hello harsh,
check t-code opsc . i think there you have tick planning indicator. if it is so then the cost will book on WBS level not on network level. due to this cost on commitment in not come.
and do one thing more run t-coe cjen it will uodated the ps info datastructure.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Harsh,
I think the PR commitment is suppressed in your system. It should update the commitment COOI and COSP table. Please check if you activate the commitment in transaction OKKP. Also please verify all the criteria listed in SAP note 47992 are fulfilled.
Regards, Gordon
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Can you check whether cost element is created for that GL Account or not?
For checking the commitments you also try it posting one FI entry (if it is test client).
Regards
Rao
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Just a guess, check if the cost element that reports the commitment is suppressed. You can take help of your FICO consultant.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.