Hi,
We have a scenario here wherein project systems allows entry of incorrect material code during PR creation. These are the steps done:
1. We have a contract with let's say material code X100.
2. User creates a PR in CJ20N referencing the contract with material code X200. Notice that the material code used here is different.
3. Save. No error from the system.
When I tried to replicate this scenario in MM using ME51N (for PR creation reference to a contract) it doesn't allow. How come CJ20N allows these incorrect entries?
Hi Jackie
When creating PR through network activities check whether you have maintained the correct Outline agreement ( contract) in the activity
Vijay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
use cnex0037 exit and validate the material code while creating PR in cj20n.
regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.