Forecast dates mandatory at WBS element

federico_gregoret
Participant
0 Kudos

Hi everyone!

We are using basic dates at network level and then with button-up scheduling we have the system calculate these dates at WBS element level. But we also need to use forecast dates only at WBS element. So we need to have these dates mandatory at WBS element level. I tried to customize this with field selection, but these fields are not available. I also tried with a validation, but neither they are available to be validated.

Any standard suggestions?

Thanks!!

Regards!

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member203098
Active Contributor
0 Kudos

By using transcation variant in cj20n we can make forcast dates mandatory. run the txn shd0 and follow the steps in cj20n as mentioned in the wiki.

http://wiki.sdn.sap.com/wiki/display/Snippets/Transaction+Variant+-+A+Step+by+Step+Guide+for+Creatio...

regards,